No Surprises that Pickles Solar Decision goes to JR

This was the worst decision in years.  This isnt an issue of whether or not you are pro- or anti the type of application,  In Planning the decision maker has to sit in a quasi judicial role and play by policy and the law and not make it up as we go along.  We first suggested this case was challengable here.

Planning Resource

The developer behind plans for a 24MW solar farm in Suffolk has confirmed that it is launching legal proceedings against communities secretary Eric Pickles over his decision to refuse its project against the advice of a planning inspector.

Lark Energy took the case to appeal after it was refused by Waveney District Council on landscape grounds in February. The size of the proposal had been reduced from 30MW following objections from local residents.

In his report, the inspector said that harm to the character and appearance of the landscape was “limited”.

However, Pickles later ruled that the damage that would have been caused to the local landscape outweighed the benefits from renewable energy generation.

His decision letter stated: “The secretary of state agrees with the inspector that the harm to the character and appearance of the area would not amount to significant adverse effects but, nevertheless, considers the effect on the character of the site, although limited, would be adverse.”

The council had already approved a solar farm to the north of the appeal site, Pickles noted. This project would have less landscape impact than the appeal proposal, he said. The project at appeal would also harm an agricultural landscape character area, he judged.

Lark Energy managing director Jonathan Selwyn said that Pickles’ decision had caused great concern in the renewables industry. He said: “It is very rare for the secretary of state to overturn an inspector’s recommendation and this was not a borderline case.

“If the secretary of state decides to ignore an inspector it clearly has serious implications.”

It was only the second solar farm project to be decided by the secretary of state, the other being a 3MW project in South Northamptonshire. But in October Pickles pledged to intervene in more renewable energy planning decisions.

One thought on “No Surprises that Pickles Solar Decision goes to JR

  1. Pingback: Pickles Reverses his Worst Decision in Recent Years | Decisions, Decisions, Decisions

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s